The project involved extensive mechanical and electrical upgrades within an active healthcare facility, requiring detailed coordination to maintain ongoing operations. A key component was a 72-hour weekend shutdown to install a new 40,000 CFM air handler, which was lifted and installed in eight separate sections.
Major scope components of this project included:
- Emergency Power: Installation of an emergency generator adjacent to the active Emergency Department, requiring careful coordination to minimize disruption to hospital operations.
- Mechanical Systems: The replacement of existing equipment with two cooling towers and two direct-expansion (DX) units, along with modifications to the complex structural steel dunnage supporting the new air handler.
- Roofing and Building Envelope: Roofing modifications and associated work to accommodate the new mechanical equipment installations.